Preventing Water Infiltration in a 40-Ft Deep Wastewater Structure with Superior Grouting

Superior Grouting stopped groundwater infiltration into an underground wastewater structure with NCFI-4RH.

About This Project

Contractor

Superior Grouting

Location

Houston, Texas

Product Used

NCFI-4RH

Learn more about NCFI-4RH

Learn more about NCFI-4RH

Problem: 

During construction of a deep wastewater structure for the City of Houston, excavation advanced to approximately 40 feet below grade when significant groundwater intrusion was encountered. A prior geotechnical borehole extended to approximately 80 feet, creating a direct vertical hydraulic pathway that allowed groundwater to migrate upward into the excavation.

To temporarily manage the inflow, the contractor installed a corrugated metal pipe (CMP) to approximately 15 feet depth, using it as a controlled collection point for groundwater. This system functioned as a relief pathway, allowing sump pumps to continuously remove water and establish a workable environment for construction.

This approach enabled placement of an initial working slab; however, groundwater continued to migrate through the same pathway beneath the slab. Without a permanent cutoff solution, ongoing infiltration posed a risk to slab integrity and prevented continuation of structural construction.
 

Solution: 

Following slab placement, Superior Grouting implemented a targeted polyurethane injection program utilizing NCFI-4RH (formerly 24-003), a hydrophobic structural polyurethane system whose reaction profile and expansion characteristics make it effective for groundwater control in wet subsurface conditions.

Injection was performed around the perimeter of the CMP and the identified hydraulic pathway, rather than directly into the active flow. Multi-depth injection points were used to intercept the migration zone and treat the surrounding soils.

As the polyurethane expanded, it permeated and displaced within the soil matrix and surrounding materials, reducing permeability and creating a continuous grout curtain around the CMP. This barrier effectively stopped groundwater infiltration into the structure.
 

Results:

Groundwater inflow was rapidly reduced during initial injections and fully controlled shortly thereafter. The grout curtain successfully eliminated the vertical migration pathway, preventing further intrusion beneath the slab.

With the pathway sealed, continuous pumping was no longer required, and the contractor was able to proceed with construction without delay. The solution provided both immediate groundwater control and long-term subsurface performance, supporting the successful completion of a critical municipal wastewater infrastructure project.
 

Preventing Water Infiltration in a 40-Ft Deep Wastewater Structure with Superior Grouting

See More Case Studies

Other

Dual-Component Systems

Geotechnical

Northwestern University Retaining Wall Sealing

Discover how Lincoln Company LLC was called in to seal a retaining wall with NCFI Geotechnical Polyurethanes.

Read More

Other

Lightweight Fill Systems

Geotechnical

Little League Light Foam Pole Setting

Setting and Stabilizing 75′ lighting poles for a little league baseball park using Strata-Fill 24-018 polyurethane.

Read More

Concrete Leveling

Dual-Component Systems

Geotechnical

Ram Jack Arizona uses NCFI TerraThane 24-003 to Stabilize 47 Rocking Slabs

Ram Jack Arizona used NCFI TerraThane 24-003 to stabilize the joints of 47 slabs, completing the initial phase of the project in approximately 12 hours.

Read More

We Have Partnership Down to a Science

We understand the challenges you face, and we’re here to help. Reach out today, and let's work together to find the best solution tailored to your needs with the highest-quality polyurethane foam products available.