Ram Jack Arizona uses NCFI TerraThane 24-003 to Stabilize 47 Rocking Slabs
Ram Jack Arizona used NCFI TerraThane 24-003 to stabilize the joints of 47 slabs, completing the initial phase of the project in approximately 12 hours.

About This Project
Contractor
Ram Jack Arizona
Location
Arizona
Product Used
Terrathane™ 24-003
Learn More About Terrathane™ 24-003
Explore ProductRam Jack Arizona was contacted by a national property management firm about some rocking slabs their tenant was experiencing. The tenant, a global pharmaceutical equipment supplier, was having issues with the slabs rocking when their forklifts traversed the slab. And with over $500M in inventory at this location, the potential of equipment damage required the issue to be repaired quickly and with minimal disruption to the tenant.
Slab settlement was the suspected culprit, and Ram Jack Arizona is adept at repairing slab settlement with polyurethane foam injection. During an onsite inspection by Ram Jack Arizona, however, the profile of the slabs did not match typical slab settlement. After working with the NCFI Geotechnical team, it was concluded that the rocking was due to “slab curling” rather than settlement.
What is slab curling? Per the article “Why Slabs Curl” by Bruce A. Suprenant, “Slab curling is a common occurrence that is caused by differences in moisture content between the top and bottom of the slab. The slab edges curl upward when the surface is drier and shrinks more or is cooler and contracts more than the bottom. The curl can result in loss of contact between the slab and subbase.”
This observation was key to recommending the correct repair method for the owner and tenant. The interior floor consists of adjoining 20’x 20’ individually poured slabs. Typically, when lifting a slab on grade, injections are started in the “deepest” part of the dip. In this case that would have been near the center of each 20’ x 20’ slab. Since the rocking was due to slab curling and not settlement, however, there was no dip in the middle of the slab to lift. And because of Ram Jack’s identification of the curling, they avoided the mistake of lifting in the center of the panel that would have raised the entirety of these relatively small slabs, including the edges, worsening the problem instead of fixing it.
Ram Jack Arizona used NCFI TerraThane 24-003 to stabilize the joints of 47 slabs, completing the initial phase of the project in approximately 12 hours. The work was completed overnight on a weekend and did not impact ongoing operations at the warehouse. The success of Ram Jack Arizona’s solution has resulted in Phase II operations to stabilize the remaining portions of the facility.
Project Gallery
Get Started with NCFI
See More Case Studies

Northwestern University Retaining Wall Sealing
Discover how Lincoln Company LLC was called in to seal a retaining wall with NCFI Geotechnical Polyurethanes.
Read More
Little League Light Foam Pole Setting
Setting and Stabilizing 75′ lighting poles for a little league baseball park using Strata-Fill 24-018 polyurethane.
Read More
North Dakota I-20 and 94 Highway Slab Lift
Erosion underneath concrete slab highway was creating unsightly and potentially dangerous driving conditions requiring a lift under I-29 and Highway 94
Read MoreWe Have Partnership Down to a Science
We understand the challenges you face, and we’re here to help. Reach out today, and let's work together to find the best solution tailored to your needs with the highest-quality polyurethane foam products available.